Irrigation board regrets Nyandarua’s Karai dam bursts

Written By: KNA
267

National Irrigation Board Chief Eng. Charles Mwasia explains why the Karai dam burst its banks to a team of administrators and experts who visited the site to assess the damage and forge a way forward.
KBC-survey-feedback-poster

The National Irrigation Board (NIB) is assuring that the construction works and repairs of the Karai water pan that burst its banks on Monday night will continue.

Chief Eng. Charles Mwasia, while regretting the incident, noted that the works of the dam located in Ndaragua Constituency were at 90 percent completion and will continue once the rains subsidize.

“The contractor is still on site and we will ensure the project is completed before we hand it over to the community. Water spillways and fencing will be done on the 100,000 cubic meter water pan to allow farmers to use it for irrigation,” he added.

Also Read  DP says universities should only offer degree courses

Speaking at the site, Eng. Mwasia, refuted claims that the NIB did not conduct public participation, adding that proper procedure was followed and the resident proposed the site.

Get breaking news on your Mobile as-it-happens. SMS ‘NEWS’ to 20153
Nyandarua County Commissioner Boaz Cherutich addresses the media on the banks of Karai daa, in Ndaragwa constituency, when he led a team of experts and administrators in assessing the damage on the 100,000 cubic meter dam that burst its banks on Monday night.

“The water pan is what was excavated and not the soil residues that was acting as the banks of the water pan,” added the chief engineer, noting that the contractor had not been paid for the works and he will need to deliver what was envisaged before money is released.

Also Read  Kenya Power rolls out campaign to enhance customer satisfaction

Nyandarua County commissioner Boaz Cherutich, who led the County Development Implementation Coordination Committee (CDICC) in a fact-finding mission on the dam regretted the incident saying that legal redress was being sought on the matter to ensure there was value for money.

Also Read  Senate team tours counties to audit leased medical equipment

The project was temporarily stopped until the chief engineer submits the Environmental Impact Assessment and plans for approval and further consultations.