KenGen’s development of 165.4MW Olkaria V Plant on course

Development of the 165.4MW Olkaria V Geothermal Power Plant is 75 percent complete and on-schedule, KenGen’s Managing Director and CEO, Mrs Rebecca Miano has said.

Two generator units, each weighing 130 metric tonnes, departed the Port of Mombasa on Thursday,  signalling the beginning of the final process towards the completion of the plant.

Upon arrival at Olkaria, the generator units will be loaded onto a 9-metre-high reinforced concrete platform called a deck using a specialized mobile hoist by a sub-contracted company from the UK.

On ground, both platforms are ready to receive the generators and the hoisting team is in place, having assembled the powerhouse crane and specialised hoisting system. The hoisting and positioning of each generator unit will take approximately 3 days with preparations before hoisting arrivalfor each taking a minimum of one week.

Already, other major equipment, such as turbine casing and condenser units, has been delivered at site.

The Olkaria V Geothermal Power Plant, whose construction commenced in January 2017, is set for commissioning in July 2019 and comprises two units under construction by the Consortium of Mitsubishi Corporation, Mitsubishi Hitachi Power Systems Ltd and H-Young & Company E.A Limited.

KenGen has an ambitious plan of developing an additional 720 MW by the year 2020.

The company’s current installed capacity is 1,631 MW.

  

Latest posts

AfDB expected to expand lending by 8% after AAA rating

Ronald Owili

Pension funds urged to tap informal sector to sustain growth

Ronald Owili

Tourism boost as Romanian charter flight lands in Mombasa

Ronald Owili

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More